Rail fixing grout
+
  • Rail fixing grout

Rail fixing grout


Rail fixing grout

GB50448-2015 Technical Code for Application of Cement-based Grouting Materials

Mobility(mm)

24h Vertical expansion rate(%)

Compressive strength(MPa)

Primary grouting thickness(mm)

Reference water consumption

Standard consumption

≥300

≥0.020

R1≥20

R3≥40

R28≥60

≤200

12%~13%

2200Kg/m3

The above data were measured under standard laboratory conditions.

 

Construction process
1. Preparation before construction:
◆ Clean the track base surface, and the track base surface shall be fully wetted 24 hours before grouting. One hour before grouting, the accumulated water shall be drained.
◆ Erect the formwork according to the grouting construction drawing, and the formwork shall not leak grout.
◆ In case of grout leakage during grouting, it shall be handled in time.

2. The process of grouting with crane rail grout material shall meet the following requirements:
◆ During secondary grouting of crane rail grout, grouting shall be conducted from one side until the other side overflows. Grouting shall not be conducted from four sides at the same time.
◆ After the grouting starts, it must be carried out continuously without interruption, and the grouting time shall be shortened as much as possible.
◆ It is strictly prohibited to vibrate during grouting. If necessary, bamboo strips can be used for pulling and diversion.
◆ The thickness of each grouting shall not exceed 150mm. When the grouting layer is less than 30mm, corresponding auxiliary measures shall be taken or other types of materials shall be used.
◆ The vibration of the running machine shall not be transmitted to the equipment foundation ready for grouting.

3. The initial setting time of CGM crane rail grout is about 3-4 hours.

4. After 3-4 hours, the initial setting shall be identified by visual inspection and hand feeling. After the initial setting is determined, the surface shall be gently troweled with a spatula, and then covered with linen or cotton cloth.

5. According to the difference of temperature, under 15℃, water curing shall be conducted once a day in the morning and once a day in the evening; 15℃C - 35°C curing with water once a day in the morning, twice a day in the afternoon and twice a day in the evening.

6. Wet curing shall be conducted for the solidified crane rail grout for at least 7 days.

Rail fixing grout is a special crane rail grout containing selected natural aggregate, with features of excellent fluidity, high compressive strength, long working time, economy, compactness, no shrinkage, no corrosion, no metal aggregate, convenient construction, continuous reinforcement, good bonding performance and toughness.

Rail fixing grout is a special crane rail grout containing selected natural aggregate, with features of excellent fluidity, high compressive strength, long working time, economy, compactness, no shrinkage, no corrosion, no metal aggregate, convenient construction, continuous reinforcement, good bonding performance and toughness.

 

Product Characteristics

1. Early strength, high strength: 1-3 days compressive strength up to 30-50Mpa above, 28 days compressive strength up to 60Mpa above.
2. High self-flowing: it can fill all the voids and meet the requirements of secondary grouting of equipment.
3. Micro-expansion: ensure the close contact between equipment and foundation, no shrinkage after the second grouting, high bond strength, and the reinforcement holding force is not less than 6Mpa.
The bond strength is high, and the holding force with the steel reinforcement is not less than 6Mpa.
4. Winter construction: outdoor construction is allowed at -10℃.
5. Strong durability: this product is an inorganic cementing material, the service life is greater than the service life of the base concrete. After millions of times of fatigue test, 50 times of freeze-thaw cycle test strength without significant changes. After 30 days of immersion in motor oil, the strength is significantly increased.

 

Product use

1. Applicable to grouting of machine base, foot bolt and other equipment foundation.
2. Strengthening, repairing and reinforcing of beams, plates, columns, foundations, floors and roads of buildings.
3. Anchoring and structural reinforcement of anchor bolts and steel bars.
4. Inlaying of construction joints in subway, tunnel, underground and other projects against the striking method.
5. Secondary grouting for the fixed connection between steel structure (steel rail, steel frame, steel column, etc.) and foundation.

 

 

 

 

 

Advantage
Product detail

GB50448-2015 Technical Code for Application of Cement-based Grouting Materials

Mobility(mm)

24h Vertical expansion rate(%)

Compressive strength(MPa)

Primary grouting thickness(mm)

Reference water consumption

Standard consumption

≥300

≥0.020

R1≥20

R3≥40

R28≥60

≤200

12%~13%

2200Kg/m3

The above data were measured under standard laboratory conditions.

 

Construction process
1. Preparation before construction:
◆ Clean the track base surface, and the track base surface shall be fully wetted 24 hours before grouting. One hour before grouting, the accumulated water shall be drained.
◆ Erect the formwork according to the grouting construction drawing, and the formwork shall not leak grout.
◆ In case of grout leakage during grouting, it shall be handled in time.

2. The process of grouting with crane rail grout material shall meet the following requirements:
◆ During secondary grouting of crane rail grout, grouting shall be conducted from one side until the other side overflows. Grouting shall not be conducted from four sides at the same time.
◆ After the grouting starts, it must be carried out continuously without interruption, and the grouting time shall be shortened as much as possible.
◆ It is strictly prohibited to vibrate during grouting. If necessary, bamboo strips can be used for pulling and diversion.
◆ The thickness of each grouting shall not exceed 150mm. When the grouting layer is less than 30mm, corresponding auxiliary measures shall be taken or other types of materials shall be used.
◆ The vibration of the running machine shall not be transmitted to the equipment foundation ready for grouting.

3. The initial setting time of CGM crane rail grout is about 3-4 hours.

4. After 3-4 hours, the initial setting shall be identified by visual inspection and hand feeling. After the initial setting is determined, the surface shall be gently troweled with a spatula, and then covered with linen or cotton cloth.

5. According to the difference of temperature, under 15℃, water curing shall be conducted once a day in the morning and once a day in the evening; 15℃C - 35°C curing with water once a day in the morning, twice a day in the afternoon and twice a day in the evening.

6. Wet curing shall be conducted for the solidified crane rail grout for at least 7 days.

概要

Rail fixing grout is a special crane rail grout containing selected natural aggregate, with features of excellent fluidity, high compressive strength, long working time, economy, compactness, no shrinkage, no corrosion, no metal aggregate, convenient construction, continuous reinforcement, good bonding performance and toughness.

Advantage
Product detail

GB50448-2015 Technical Code for Application of Cement-based Grouting Materials

Mobility(mm)

24h Vertical expansion rate(%)

Compressive strength(MPa)

Primary grouting thickness(mm)

Reference water consumption

Standard consumption

≥300

≥0.020

R1≥20

R3≥40

R28≥60

≤200

12%~13%

2200Kg/m3

The above data were measured under standard laboratory conditions.

 

Construction process
1. Preparation before construction:
◆ Clean the track base surface, and the track base surface shall be fully wetted 24 hours before grouting. One hour before grouting, the accumulated water shall be drained.
◆ Erect the formwork according to the grouting construction drawing, and the formwork shall not leak grout.
◆ In case of grout leakage during grouting, it shall be handled in time.

2. The process of grouting with crane rail grout material shall meet the following requirements:
◆ During secondary grouting of crane rail grout, grouting shall be conducted from one side until the other side overflows. Grouting shall not be conducted from four sides at the same time.
◆ After the grouting starts, it must be carried out continuously without interruption, and the grouting time shall be shortened as much as possible.
◆ It is strictly prohibited to vibrate during grouting. If necessary, bamboo strips can be used for pulling and diversion.
◆ The thickness of each grouting shall not exceed 150mm. When the grouting layer is less than 30mm, corresponding auxiliary measures shall be taken or other types of materials shall be used.
◆ The vibration of the running machine shall not be transmitted to the equipment foundation ready for grouting.

3. The initial setting time of CGM crane rail grout is about 3-4 hours.

4. After 3-4 hours, the initial setting shall be identified by visual inspection and hand feeling. After the initial setting is determined, the surface shall be gently troweled with a spatula, and then covered with linen or cotton cloth.

5. According to the difference of temperature, under 15℃, water curing shall be conducted once a day in the morning and once a day in the evening; 15℃C - 35°C curing with water once a day in the morning, twice a day in the afternoon and twice a day in the evening.

6. Wet curing shall be conducted for the solidified crane rail grout for at least 7 days.

概要

Rail fixing grout is a special crane rail grout containing selected natural aggregate, with features of excellent fluidity, high compressive strength, long working time, economy, compactness, no shrinkage, no corrosion, no metal aggregate, convenient construction, continuous reinforcement, good bonding performance and toughness.

Online Message

Need help?

Let's ask your questions


Related Product Recommendations

undefined

undefined

Product Documentation

If you do not have a comprehensive understanding of our products, we have uploaded relevant technical documents for you to download and reference so that you can better understand our product usage and technical parameters

View More
图片名称

Online Message

If you are interested in our products and would like to learn more details, please leave a message here and we will reply to you as soon as possible.

Submit